This site reported in September that Tunbridge Wells Borough Council had set a timetable for deciding whether its Royal Victoria Place (RVP) overhaul actually goes ahead, with a final vote pencilled in for 11 November. That date has arrived: Full Council meets on Wednesday evening to sign off the budget for the Palm Court phase, having already been recommended for approval by Cabinet on 22 October.
How we got here
Done · July 2025
Full Council backs a £42m–£68m feasibility study for the three-zone RVP overhaul
Done · 8 September 2026
Council publishes the timetable: Cabinet on 22 October, Full Council on 11 November
Done · 10 September 2026
Camden Road listing bid rejected by DCMS, clearing a key obstacle for Ely Court
Done · 22 October 2026
Cabinet recommends Full Council approve the Palm Court budget
Decision point · This week, 11 November 2026
Full Council votes on the £23.5m Palm Court budget, at an Extraordinary meeting with no public questions
Conditional · April 2027 or later
Ely Court's cinema-led scheme only goes ahead if a further report endorses it
The number: £23.5m
The council is being asked to approve an additional £23.5m capital budget for Palm Court, on top of the £3.3m already approved in July 2025 - a total approaching £27m for this phase alone. When the wider three-zone RVP redevelopment (Ely Court, Palm Court and Market Square) went through feasibility study in 2025, the full scheme was costed at between £42m and £68m; the council's report says Palm Court's £23.5m sits within that original range as designs have firmed up through the architects' RIBA stages.
Where the £26.8m comes from
The £23.5m being voted on this week isn't the whole Palm Court budget - it sits on top of £3.3m Full Council already approved in July 2025 to get the scheme to this stage. Together, that's £26.8m committed to Palm Court alone before a single zone of the wider RVP scheme is finished.
Approved July 2025
New ask, going to Full Council 11 Nov
= £26.8m committed to Palm Court so far
Market Square homes paused
When the plan was first announced, the council described a three-part scheme: leisure-led uses at Ely Court, more retail space at Palm Court, and homes on Market Square. This week's report confirms that development proposals for Market Square "are not progressed as part of the Full Scheme at this stage" - a pause on the homes element that wasn't part of what was previously announced, though the report doesn't rule it out permanently.
Ely Court's cinema plans stay conditional
Ely Court - where a boutique cinema and leisure and restaurant units are proposed, and where a listing bid for the former Friendly Societies Hall on Camden Road was rejected by the Department for Culture, Media and Sport back in September - isn't being abandoned. The council wants to include it in the same contractor procurement process as Palm Court, to "preserve the Council's position" and avoid delays if it does go ahead. But the report is explicit that Ely Court will only actually proceed "if endorsed by Full Council following a further report" in April 2027 "or at a later date as may be required" - the same month a decision on the full scheme was originally pencilled in when this site first reported the timetable.
Councillors are also being asked to approve a £400,000 budget to begin procuring a two-stage design-and-build contractor, and to create an "RVP Development Reserve" to manage the scheme's receipts and payments going forward. Notably, Wednesday's meeting is designated an Extraordinary Full Council meeting, and the published agenda states there will be no ability for members of the public or councillors to submit questions - a departure from how ordinary Full Council meetings normally run. Source:
Tunbridge Wells Borough Council, Full Council agenda, 11 November 2026